Description
The US$3 billion Belgrade Waterfront development is situated between Belgrade’s historic old town (“Stari Grad”) and the new district of Novi Beograd, an enormous urban complex rising on the right bank of the Sava River. Once completed, the 1.8 million m2 of gross construction area will comprise 250,000 m2 of office space, 7,000 apartment units, and eight hotels.
Products Used
Beton Plus, the ready-mix concrete supplier, mixed PENETRON ADMIX into 25,000 m3 (32,700 yds3) of concrete for the structures of two basement floors to counter the high hydrostatic pressure from groundwater levels exacerbated by the nearby Sava River. Approximately 8,000 m (5 miles) of PENEBAR waterstop strips were used to seal the construction joints.
Related Media Releases
February 1, 2022